- Updated at 02/10/2026, 13:43High humidity in railway maintenance environments can accelerate oxidation and corrosion, potentially affecting metal components, equipment, and technical materials. Maintaining a dry and stable environment is therefore essential to protecting critical assets and extending their operational lifespan.
To minimize moisture-related risks, the facility selected Kosmen dehumidifiers for its elevated railway maintenance area. The solution was designed to maintain suitable humidity conditions, protect equipment and technical materials, and support stable railway maintenance operations.

Delivery of 16 Kosmen KM-90S industrial dehumidifiers
Project Overview
Project Information
- Location: Hanoi, Vietnam
- Sector: Construction & Infrastructure
- Industry: Railway
- Application: Humidity control for an elevated railway maintenance facility
- Equipment Installed: 16 Kosmen KM-90S Industrial Dehumidifiers
- Installation Objective: Maintain relative humidity at 45–55% RH to reduce moisture-related oxidation, corrosion, and deterioration of machinery, components, and technical materials, while providing suitable environmental conditions for railway maintenance and operations.
Performance After Installation
- Maintains relative humidity at 45-55% RH, meeting the environmental requirements of the maintenance facility.
- Reduces moisture exposure on machinery, components, and metal surfaces, helping minimize oxidation and corrosion.
- Maintains more consistent humidity levels and reduces fluctuations throughout the controlled area.
- Provides a dry environment for equipment storage and maintenance activities.
- Supports continuous moisture removal through high dehumidification capacity and reliable long-term operation.

Delivery of Kosmen KM-90S industrial dehumidifiers in Hanoi
Kosmen’s Project Survey, Consultation, Installation & Implementation Process
Stage 1: Understanding the Customer’s Requirements
Kosmen received an inquiry from a railway facility in Hanoi seeking a humidity control solution for its elevated railway maintenance area. The facility required a consistently dry environment to minimize the effects of excess moisture on machinery, components, and technical materials used in railway maintenance and operations.
Based on the initial requirements, Kosmen gathered information on the characteristics of the facility, the target humidity range, and operating conditions. These details were then forwarded to the technical team to prepare for the site survey and develop an appropriate solution.
Stage 2: Information Gathering & Initial Consultation
Following the initial consultation, Kosmen assessed the facility layout, equipment and component characteristics, technical materials, and operating conditions to identify factors that could affect dehumidification performance.
The customer required a dehumidifier capable of maintaining relative humidity at 45-55% RH to help reduce the risk of oxidation and corrosion associated with high-humidity conditions. This information allowed Kosmen’s technical team to establish the initial technical requirements and determine the direction of the humidity control solution.
Stage 3: Site Survey Confirmation
Once the initial requirements had been established, Kosmen coordinated with the customer to schedule an on-site survey at the elevated railway maintenance facility in Hanoi. Both parties confirmed the survey schedule, scope, and key areas to be inspected, allowing the technical team to prepare thoroughly before arriving on site.
Kosmen prepared the necessary measuring instruments and technical documentation for the survey. Environmental conditions and other relevant parameters were recorded on site to support the subsequent assessment, system calculations, and solution design.
Stage 4: On-Site Survey & Technical Consultation
As scheduled, Kosmen’s technical team visited the elevated railway maintenance facility in Hanoi to assess the actual operating environment. The survey covered ambient humidity, airflow conditions, machinery layout, and other factors that could influence dehumidification performance.

Kosmen technical consultation and support
The survey identified an area of approximately 1,350 m² requiring humidity control, with a target range of 45–55% RH. Based on the on-site data, Kosmen calculated the required capacity of the industrial dehumidifiers and determined an appropriate equipment layout to suit the facility’s operating conditions.
Stage 5: Solution Proposal & System Layout
Kosmen provides free on-site surveys and humidity control consultation to help customers identify solutions suited to their actual operating conditions. Based on the data collected at the facility, Kosmen’s technical team calculated the required capacity and recommended 16 Kosmen KM-90S industrial dehumidifiers, providing sufficient dehumidification capacity for the large maintenance area and continuous operation.
In addition to equipment selection, Kosmen developed a detailed placement plan for each controlled area. The installation positions were determined to support effective air circulation, minimize localized moisture buildup, and avoid interfering with maintenance and railway operations.
Stage 6: Solution Approval & Contract Signing
After finalizing the technical proposal, Kosmen and the customer confirmed the deployment of 16 Kosmen KM-90S industrial dehumidifiers, including equipment quantity, installation locations, implementation schedule, and related terms.
Once both parties reached an agreement, the contract was signed and the implementation plan was officially confirmed. Kosmen then prepared the equipment, technical personnel, and installation arrangements to ensure the project was completed according to the agreed schedule.
Stage 7: Delivery, Installation & Commissioning
According to the project schedule, 16 Kosmen KM-90S industrial dehumidifiers were delivered to the elevated railway maintenance facility in Hanoi. Kosmen’s technical team positioned the units according to the approved layout, completed the installation, and inspected each unit before operation.

Kosmen KM-90S industrial dehumidifiers at railway maintenance facility
Following installation, the entire system was test-run and monitored on site to verify equipment performance and humidity control capability. Once the system met the required technical conditions, Kosmen and the customer’s representatives completed the final inspection and handover, officially putting the system into operation.
Stage 8: Operational Training & After-Sales Support
Following the system handover, Kosmen’s technical team provided on-site training on the operation of all 16 KM-90S industrial dehumidifiers. The training covered humidity settings, operating status monitoring, routine cleaning, and periodic maintenance to help ensure stable equipment performance throughout its service life. Kosmen also provided technical documentation, warranty information, and operating guidelines to support effective system management.
Beyond operational training, Kosmen continues to support the customer through comprehensive after-sales policies:
- Technical consultation tailored to the customer’s actual operational requirements.
- Special pricing policies for large-volume projects.
- 30-day one-for-one replacement for products with verified manufacturing defects.
- 24-month equipment warranty and compressor warranty of up to 36 months.
- Periodic maintenance once per year, with a maximum of two maintenance visits for industrial dehumidifier models.
With extensive experience in industrial humidity control solutions, Kosmen is pleased to serve as a trusted partner in protecting machinery, equipment, and technical materials at the elevated railway maintenance facility. From technical consultation and installation to ongoing after-sales support, Kosmen remains committed to supporting reliable and efficient operations throughout the system’s lifecycle.
KOSMEN - PIONEERING SOLUTIONS FOR HUMIDITY CONTROL & AIR QUALITY
- Head Office: No. 77 Dinh Thi Thi Street, Van Phuc City Residential Area, Hiep Binh Ward, Ho Chi Minh City
- Representative Office: No. 27B Street No. 12, Hiep Binh Ward, Ho Chi Minh City
- Hanoi Office: No. NV 4.7, Cau Buou New Urban Area, Thanh Liet Ward, Hanoi City
- Da Nang Office: No. 41 Vo An Ninh Street, Hoa Xuan Ward, Da Nang City
- Da Lat Office: No. 38/7, Ba Thang Hai Alley, Xuan Huong - Da Lat Ward, Lam Dong Province
- Hotline: 0766 899 799 (Northern Region) - 0935 696 695 (Central Region) - 0965 210 874 (Southern Region) - 0975 359 877 (Central Highlands)
- Website: https://kosmen.com.vn/en